Project database for project team only. Last update 1.8.2019:
- Client – OHEL DAVID SYNAGOGUE
- Contractor (principle contractor) –
- Architect (principle designer) – mail@spaceagent.com
- CDM Consultant –
- Structural Engineer – Mervyn
- Party Wall Surveyor – Mervyn
- Building Control –
- M+E Consultant –
- Steelwork supplier –
- Staircase supplier –
- Glazing supplier
- Roofing supplier
BRIEF 10%
A. Inception
- Aerial view (bing)
- Site map (google)
- BARNET – planning history
B. Feasibility
DESIGN 35%
C. Outline design (client)
- BWL_P10a – agreed scheme April 2019
D. Scheme design (planning)
E. Technical design (building control)
SPECIFICATION 70%
F. Production information
G. Tender documentation
H. Tender action (contractor)
CONSTRUCTION 100%
I. Appointment
J. Construction
L. Completion